State answers FERC questions about Cook Inlet pipeline crossing  By Larry Persily paper@alaskan.com June 4, 2019 Larry Persily, former Alaska gas pipeline federal coordinator. NGP Photo by Dave Harbour. The state-led gas line development team has told federal regulators it is confident the Alaska LNG project’s steel pipeline could withstand Cook Inlet’s strong currents, shifting seabed and traveling boulders along the 29-mile underwater route to the gas liquefaction plant in Nikiski, on the Kenai Peninsula. The water-crossing information is among the remaining batches of answers the Alaska Gasline [...]